January 30, 2019 – Bob Hope Village 6 Phase 1 Update from Lord and Son Construction, Inc.

Site clearing has been progressing with trees and debris being cleared out. Soil has been added to aid in compaction for the foundation. Layout and formwork will begin for the main buildings.  

Utilities and stormwater will be the next focus of the project. Utilities including conduits for communication lines and electrical power will be placed underground throughout the complex. Water mains, fire sprinkler, and sewer and storm pipes will be placed in the coming weeks.

Follow the Air Force Enlisted Village’s Facebook page for weekly photo updates as the project landscape will change quickly.